The route for Nine Mile Creek Regional Trail through Edina is not yet determined. Several alternative trail routes are under consideration and include routes adjacent to roads and along the Nine Mile Creek corridor. As part of the evaluation process for the alternative trail routes, the Park District and City worked together to conduct an Environmental Assessment and Community Assessment Team.
The Environmental Assessment was completed by an independent consulting and utilized a common environmental review practice called an Environmental Review Worksheet. The Community Assessment Team was comprised of neighborhood representatives which provided guidance in the completion of Social, Technical, and Economic Assessments. The completed Environmental, Social, Technical, and Economic Assessments are available for review.
The Park District conducted a 30-day public comment period between June 14 and July 14, 2010 and two identical open houses for community meember to learn more about assessment findings and provide written feedback. The public comment period is now closed.
Environmental Assessment
As part of the assessment process, Three Rivers Park District completed a volunteer environmental assessment worksheet (EAW). On July 7, 2009, the City of Edina passed a Resolution of Support for the completion of the EAW.
The EAW findings will help determine if any alternative trail routes should be removed from further consideration and will help determine the preferred Nine Mile Creek Regional Trail route through Edina. The EAW is complete and available for review.
(All files are PDFs)
Environmental Assessment Worksheet
Appendix A: Figures pp. 1-7 | pp. 8-15 | pp. 16-20
Appendix B: Regional Trail Maintenance Standards and Plan
Appendix C: DNR Natural Heritage Information
Appendix D: MN RAM Study
Appendix E: Parking Study
Appendix F: Cultural Resource Information Correspondence
Appendix G: Viewshed Graphics
See more information on the EAW process and scope.
Community Assessment Team
The Park District coordinated a Community Assessment Team comprised of representatives from each of the 14 alternative trail routes under consideration. The Community Assessment Team representatives were nominated by property owners living adjacent the alternative trail routes in early Fall 2009.
Download the Community Assessment Team Contact List.
The Community Assessment Team role was to identify the constraints and opportunities associated with each route, provide design suggestions/considerations for each route, and convey information back to their respective route neighbors. The resulting Social, Technical, and Economic Assessment findings are complete and available for public review. These findings will help determine if any alternative trail routes should be removed from further consideration and will help determine the preferred Nine Mile Creek Regional Trail route through Edina. The 30-day public period for the social, technical and economic findings closed on July 14, 2010.
(All files are PDFs)
Cover Letter
Executive Summary
Project Background
Route Summary 1 | 2 | 3 | 4 | 5 | 5D | 5E | 5F | 7 | 8 | 9 | 11 | 13 | 19 | 20
Conclusion
Appendix: Route Maps
Appendix: Methodology
Appendix: Social Assessment Tables
Appendix: Technical Assessment Tables
Appendix: Economic Assessment Table
The Community Assessment Team met approximately every four to six weeks between December 2009 and May 2010. Meeting agendas, presentations, and minutes are available below.
Meeting information
(All files are PDFs)
• December 2, 2009: Agenda | Presentation | Meeting Minutes
• January 13, 2010: Agenda | Presentation | Meeting Minutes
• February 17, 2010: Agenda | Presentation | Meeting Minutes
• April 5, 2010: Agenda | Presentation | Meeting Minutes
• May 17, 2010: Agenda | Handouts 1 • 2 • 3 | Meeting Minutes
Frequently Asked Questions
Have questions that still aren’t answered? Review the frequently asked questions and answers. (Last updated June 2010)
Comments?
Offer your comments through one of the following options.
Write Us
Three Rivers Park District
Attn. Nine Mile Creek Regional Trail
3000 Xenium Lane
Plymouth, MN 55441
E-mail Us
To send comments via e-mail contact ninemilecreektrail@ThreeRiversParkDistrict.org
See more information on Nine Mile Creek Regional Trail.